    Vaughn Palmer: Site C hits a milestone, but B.C. NDP not cheering

    kitsiosgeo by kitsiosgeo
    August 16, 2023
    in Canada
    0
    Vaughn Palmer: Site C hits a milestone, but B.C. NDP not cheering

    [ad_1]

    Breadcrumb Trail Links

    Opinion News Local News Energy Columnists Business

    Opinion: Given Site C’s history of cost overruns, engineering problems and political woes, celebrations should wait until the power plant is fully operational

    Get the latest from Vaughn Palmer straight to your inbox Sign Up

    Published Aug 16, 2023  •  Last updated 1 hour ago  •  4 minute read

    Final touches are put on the earth-filled dam at the B.C. Hydro Site C electric project on the Peace River near Fort St. John, in July.
    Final touches are put on the earth-filled dam at the B.C. Hydro Site C electric project on the Peace River near Fort St. John, in July. Photo by B.C. Hydro /Government of B.C.

    Article content

    VICTORIA — B.C. Hydro this week reported record electricity consumption as sweltering customers turned on air conditioners and fans in unprecedented numbers.

    “Electricity demand record for August broken amid heat wave,” read the headline on the news release Tuesday.

    Article content

    Still, the demand was only about three quarters of peak loads “during the coldest and darkest days of the year.”

    Advertisement 2

    This advertisement has not loaded yet, but your article continues below.

    Vancouver Sun

    THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

    Subscribe now to read the latest news in your city and across Canada.

    Unlimited online access to articles from across Canada with one account. Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on. Enjoy insights and behind-the-scenes analysis from our award-winning journalists. Support local journalists and the next generation of journalists. Daily puzzles including the New York Times Crossword.

    SUBSCRIBE TO UNLOCK MORE ARTICLES

    Subscribe now to read the latest news in your city and across Canada.

    Unlimited online access to articles from across Canada with one account. Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on. Enjoy insights and behind-the-scenes analysis from our award-winning journalists. Support local journalists and the next generation of journalists. Daily puzzles including the New York Times Crossword.

    REGISTER TO UNLOCK MORE ARTICLES

    Create an account or sign in to continue with your reading experience.

    Access articles from across Canada with one account. Share your thoughts and join the conversation in the comments. Enjoy additional articles per month. Get email updates from your favourite authors.

    Article content

    The utility went on to assure customers that “its renewable and reliable hydroelectric system can meet the additional demand.”

    For now anyway.

    As Premier David Eby conceded back in June, Hydro is forecasting a 15 per cent increase in demand over the next few years. He said the utility needs to acquire an additional 3,000 gigawatt hours of electricity “as early as 2028,” enough to power 270,000 homes.

    That target is in addition to the roughly 5,000 GWh a year to be produced by Site C, enough for 450,000 homes. The giant hydroelectric dam on the Peace River is scheduled to be fully operational by the end of 2025.

    Happily for the New Democrats, B.C. Hydro was able to report some good news in that regard recently, when it announced “a major milestone on the Site C project with the completion of the earth fill dam.”

    “The earth-fill dam stands about 60 metres tall (the height of a 20-storey building), stretches more than one kilometre across the Peace River and is about 500 metres wide at its base,” boasted the news release. “In total about 16 million cubic metres of earth-fill material was placed.”

    Westcoast Homes

    Stay on top of the latest real estate news and home design trends.

    By clicking on the sign up button you consent to receive the above newsletter from Postmedia Network Inc. You may unsubscribe any time by clicking on the unsubscribe link at the bottom of our emails or any newsletter. Postmedia Network Inc. | 365 Bloor Street East, Toronto, Ontario, M4W 3L4 | 416-383-2300

    Thanks for signing up!

    A welcome email is on its way. If you don’t see it, please check your junk folder.

    The next issue of West Coast Homes will soon be in your inbox.

    We encountered an issue signing you up. Please try again

    Article content

    Advertisement 3

    This advertisement has not loaded yet, but your article continues below.

    Article content

    With those superlatives, one might have expected the provincial government to handle the announcement with more than a one-page news release.

    Cabinet ministers in hard hats. Validators from the union, the community and Indigenous nations.Perhaps there’d be the premier himself at the wheel of the machinery to deposit the last load of those 16 million cubic metres of earth.

    Still, the New Democrats did nothing to mark the topping up of the earth fill dam.

    Granted, B.C. Liberal Premier Christy Clark approved Site C, oversaw the start of construction eight years ago and fulfilled her vow to get it “past the point of no return” before she lost her legislative majority in 2017.

    The New Democrats haven’t hesitated to take credit for other projects — housing, highways, health care facilities — that were started on the watch of the previous government.

    Why not Site C?

    The New Democrats took ownership of the project not once, but twice: in 2017 when they decided to continue construction and again in 2021 when they pressed on despite the discovery of geotechnical instabilities in the foundations of the dam.

    Advertisement 4

    This advertisement has not loaded yet, but your article continues below.

    Article content

    The project remains a source of embarrassment to the New Democrats in political terms.

    In Opposition, they were against building Site C, insisting the power wasn’t needed. It led more than a few of their own supporters to believe they would kill it if they took office.

    “Site C Sucks,” declared then leader, soon to be premier, John Horgan in a posting still accessible on the internet.

    Despite the NDP government’s two approvals, the project remains controversial among supporters who deplore the flooding of agricultural land and the trampling of Indigenous rights. Others would substitute smaller scale renewables like wind, solar and geothermal power.

    Perhaps, too, the New Democrats have been scanning the fine print of B.C. Hydro’s updates on the project.

    Officially, Hydro says Site C is “on track” and due to be completed within the current $16 billion budget. That’s Hydrospeak for a year late and costing twice as much as the initial budget.

    In Hydro’s latest update on the project to the B.C. Utilities Commission, posted in June, the utility added a few caveats about things that could still go wrong at Site C:

    Advertisement 5

    This advertisement has not loaded yet, but your article continues below.

    Article content

    • “Right bank foundation enhancements at approach channel require additional work.”

    • “Tunnel conversion delayed due to constructability, condition, safety or operational issues.”

    • “Increasing regulatory requirements relating to management of potentially acid-generating rock.”

    Plus, for connoisseurs of the B.C. Hydro footnote, there was this admission at the bottom of page 45:“The list of risks and opportunities do not include (those) that are subject to confidentiality obligations or solicitor-client privilege, or that disclose commercially sensitive information relating to matters that are currently outstanding, including procurements and negotiations that are in progress at the time of this report, the disclosure of which would be harmful to B.C. Hydro’s commercial interests.”

    Never mind Hydro’s political interests.

    Though Hydro reported in June that Site C was 75 per cent complete (and the budget 70 per cent spent), much remains to be done.

    Hydro is not sure if it will be ready to begin filling the reservoir this fall or have to leave it to next year.

    Advertisement 6

    This advertisement has not loaded yet, but your article continues below.

    Article content

    The first of six generating units is scheduled to begin operating two months after the October 2024 election. The last of the six is supposed to come on line at the end of 2025.

    Given what has gone before, whichever party forms government after the next election might want to wait until Site C is fully operation before staging any celebration.

    vpalmer@postmedia.com

    Early afternoon traffic on the Trans-Canada Highway at 264th Street in Langley on Aug. 11, 2023.

    Vaughn Palmer: NDP ditch election promise on Hwy. 1 widening

    Dr. Bonnie Henry gets her first dose of COVID-19 vaccine in late 2020.

    Vaughn Palmer: B.C. should go it alone with a truly independent review of COVID response

    B.C. Premier David Eby.

    Vaughn Palmer: B.C. NDP signals it won’t allow city ‘poison pills’ to multi-family buildings

    Summer subscription sale: Our in-depth journalism is possible thanks to the support of our subscribers. For a limited time, you can get full online access to The Vancouver Sun and The Province, along with the National Post and 13 other Canadian news sites, for just $40 for one year or $1 a week for 52 weeks. Support our journalism by subscribing today: The Vancouver Sun | The Province.

    Article content

    Share this article in your social network

    Comments

    Postmedia is committed to maintaining a lively but civil forum for discussion and encourage all readers to share their views on our articles. Comments may take up to an hour for moderation before appearing on the site. We ask you to keep your comments relevant and respectful. We have enabled email notifications—you will now receive an email if you receive a reply to your comment, there is an update to a comment thread you follow or if a user you follow comments. Visit our Community Guidelines for more information and details on how to adjust your email settings.

    Join the Conversation

    Advertisement 1

    This advertisement has not loaded yet, but your article continues below.

    [ad_2]

    Source link

    Tags: B.CcheeringHitsMilestoneNDPPalmerSiteVaughn
    Previous Post

    Gas, power prices pump Origin to billion-dollar profit

    Next Post

    Two pedestrians struck by car in Montreal North

    Next Post
    Two pedestrians struck by car in Montreal North

    Two pedestrians struck by car in Montreal North

    Leave a Reply Cancel reply

    Your email address will not be published. Required fields are marked *

    CATEGORIES

    • Africa
    • Asia Pacific
    • Australia
    • Business
    • Canada
    • Cryptocurrency
    • Economy
    • Entertainment
    • Europe
    • Gossips
    • Health
    • India
    • Lifestyle
    • Middle East
    • New Zealand
    • Politics
    • Sports
    • Technology
    • Travel
    • UK
    • USA

    LATEST UPDATES

    • How To Apply For A Visa For Armenia
    • Starmer pushed on EU youth mobility as Tory leadership rivals make final pitch – live
    • Aamir Khan offers condolences after ex-wife Reena Dutta’s father passes away

        © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.

        No Result
        View All Result

            © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.