    Varcoe: Trans Mountain CEO expects opening of pipeline expansion by end of March, potential sale within two years

    kitsiosgeo by kitsiosgeo
    October 5, 2023
    in Canada
    0
    Varcoe: Trans Mountain CEO expects opening of pipeline expansion by end of March, potential sale within two years

    [ad_1]

    Breadcrumb Trail Links

    Energy Columnists Business

    ‘I would say in terms of the construction, we’re in the ninth inning,’ Trans Mountain Corp. CEO Dawn Farrell said in her first interview since taking the job

    Get the latest from Chris Varcoe, Calgary Herald straight to your inbox Sign Up

    Published Oct 05, 2023  •  Last updated 5 hours ago  •  5 minute read

    Trans Mountain Corporation CEO Dawn Farrell
    Trans Mountain Corporation CEO Dawn Farrell at the company’s downtown Calgary offices on Thursday, Oct. 5. Gavin Young/Postmedia

    Article content

    Trans Mountain Corp. CEO Dawn Farrell says the oil pipeline expansion project is on track to begin commercial operations by the end of March, but acknowledges the mammoth development still faces pressures as construction enters the home stretch.

    In her first interview since taking on the job as chief executive of the federal Crown corporation, Farrell said the $30.9-billion project remains “in that range,” with only 16 kilometres of pipeline left to put in the ground.

    Advertisement 2

    This advertisement has not loaded yet, but your article continues below.

    Calgary Herald

    THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

    Subscribe now to read the latest news in your city and across Canada.

    Unlimited online access to articles from across Canada with one account.Get exclusive access to the Calgary Herald ePaper, an electronic replica of the print edition that you can share, download and comment on.Enjoy insights and behind-the-scenes analysis from our award-winning journalists.Support local journalists and the next generation of journalists.Daily puzzles including the New York Times Crossword.

    SUBSCRIBE TO UNLOCK MORE ARTICLES

    Subscribe now to read the latest news in your city and across Canada.

    Unlimited online access to articles from across Canada with one account.Get exclusive access to the Calgary Herald ePaper, an electronic replica of the print edition that you can share, download and comment on.Enjoy insights and behind-the-scenes analysis from our award-winning journalists.Support local journalists and the next generation of journalists.Daily puzzles including the New York Times Crossword.

    REGISTER TO UNLOCK MORE ARTICLES

    Create an account or sign in to continue with your reading experience.

    Access articles from across Canada with one account.Share your thoughts and join the conversation in the comments.Enjoy additional articles per month.Get email updates from your favourite authors.

    Article content

    Article content

    Once construction is complete, it will allow for testing, commissioning work and filling the line with 4.5 million barrels of oil, which should begin near the end of January.

    Concluding a long-awaited sale of the pipeline back into private-sector hands could happen potentially in early 2025, she said in a wide-ranging discussion on the project’s future.

    “I would say in terms of the construction, we’re in the ninth inning. So, we’re getting close to finishing,” Farrell, who took over the corporation’s helm in August 2022, said Thursday.

    “We’re aiming to have first oil to (the Westridge Marine Terminal) by the end of the first quarter of 2024 . . . As long as we don’t run into sort of geological risks, I feel very confident that we’re in that time frame.”

    Ottawa bought the pipeline from Kinder Morgan Canada in 2018 for $4.4 billion after it appeared the owners were set to walk away from the development.

    Related Stories

    Contruction continues on the Trans Mountain Pipeline expansion project near Valemount, B.C., in 2020.

    Regulator rules in favour of Trans Mountain route deviation, avoiding nine-month delay

    A new report says the coming startup of the Trans Mountain pipeline will help boost Canadian oil production to an all-time record high within the next two years. Workers lay pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023.

    Trans Mountain pipeline will push Canadian oil output to new heights: report

    Pipe for the Trans Mountain pipeline is unloaded in Edson, Alta. on June 18, 2019.

    Braid: Will Trudeau’s climate zealots ever cut the ribbon on Trans Mountain pipeline?

    The estimated cost of the Trans Mountain pipeline expansion project has increased once again, this time to $30.9 billion. That's an increase from the $21.4 billion price tag placed on the project a year ago, and more than double an earlier estimate of $12.6 billion. Construction of the pipeline is pictured near Hope, B.C., Monday, Oct. 18, 2021.

    Trans Mountain pipeline construction costs balloon again, this time to $30.9B

    Calgary Herald Headline News

    Headline News

    Get the latest headlines, breaking news and columns.

    By signing up you consent to receive the above newsletter from Postmedia Network Inc.

    Thanks for signing up!

    A welcome email is on its way. If you don’t see it, please check your junk folder.

    The next issue of Headline News will soon be in your inbox.

    We encountered an issue signing you up. Please try again

    Article content

    Advertisement 3

    This advertisement has not loaded yet, but your article continues below.

    Article content

    The Trans Mountain expansion project is seen as a critical piece of energy infrastructure for Canada’s oil sector, nearly tripling the capacity of the existing pipeline to 890,000 barrels per day.

    The 1,150-kilometre pipeline runs from the Edmonton area to a terminal in Burnaby, B.C.

    Oil and refined products shipped on the line will be able to access growing markets in Asia, although many analysts believe much of the crude could end up moving south to U.S. customers.

    Farrell, the former CEO of Calgary-based TransAlta Corp., remains confident the pipeline will deliver economic value for the country, even as critics expect the federal government will likely have to take a writedown to eventually sell the development.

    The capital costs have escalated from $5.4 billion in 2013 to now top $30 billion.

    “I think we’re close (on the latest price tag). For sure, there’s pressure on it because every time there’s a bit of a delay or you have to do a regulatory hearing, or you have to find a new methodology, that puts pressure on the contingency and on the reserve. But we are close, in that range,” she added, noting rising interest rates are another factor.

    Advertisement 4

    This advertisement has not loaded yet, but your article continues below.

    Article content

    “The biggest pressure on this project right now is the timing, for sure. So every month of delay is $200 million that accrues to the project.”

    Trans Mountain pipeline
    Pipes for the Trans Mountain pipeline are unloaded in Edson, Alta. Photo by Jason Franson /The Canadian Press

    The journey to get the development built is one for the Canadian history books, complete with regulatory and legal delays, changing timelines and rising budgets, the challenges of building essential infrastructure during a pandemic — and plenty of politics.

    It also comes as other proposed oil pipelines, including Northern Gateway, Keystone XL and Energy East failed to launch.

    The original Trans Mountain line was constructed 70 years ago; an application to move ahead with the expansion project was filed with Canadian regulators a decade ago.

    It received initial approval in 2016, after the regulator determined the initiative was in Canada’s public interest.

    The project has staunch supporters, including the Alberta government.

    Shippers have signed up for long-term contacts to take up about 80 per cent of the available capacity, although there are some disagreements over the pipeline’s proposed tolls, given the rising construction tab.

    Advertisement 5

    This advertisement has not loaded yet, but your article continues below.

    Article content

    “It’s a critical piece of infrastructure,” said Tristan Goodman, president of the Explorers and Producers Association of Canada.

    The development also has detractors who believe the Canadian government will end up losing money on Trans Mountain.

    Ottawa has provided loan guarantees to Trans Mountain, including $10 billion in such guarantees in 2022, according to Reuters.

    “I will be very surprised if the final price tag is the current budget of $30.9 billion,” said Eugene Kung, a staff lawyer with West Coast Environmental Law.

    “Its legacy is going to be one of the biggest and most expensive mistakes by a federal government.”

    Canada is the world’s fourth-largest oil producer and output next year could potentially increase by 250,000 barrels per day, according to S&P Global Commodity Insights.

    Trans Mountain Pipeline construction
    Contruction continues on the Trans Mountain Pipeline expansion project near Valemount, B.C., in 2020. Photo by Courtesy, Trans Mountain Pipeline /Postmedia Network

    The pipeline expansion is needed and will help prevent the discount facing western Canadian heavy oil from widening sharply during periods of pipeline constraints, said S&P vice-president Kevin Birn.

    “Canada needs this pipeline to prevent differential blowouts in the future. It needs it from a strategic point of view, being able to access global markets,” Birn said.

    Advertisement 6

    This advertisement has not loaded yet, but your article continues below.

    Article content

    “It potentially could be the last major new incremental pipeline being completed (in Canada).”

    Farrell said the project will generate about $40 billion over two decades of additional royalties and taxes to Alberta, and $12 billion in additional taxes to the federal government.

    The federal government has said it will sell the project, once it is fully derisked, and Indigenous groups have expressed interest in buying a stake.

    As for the potential of a writedown, there are efforts to minimize that from happening.

    “What I’m trying to do is minimize any capital that’s left behind, because effectively what happened here is the federal government has used the credit card of the federal government to fund this project. And once the project transfers to the private sector, we’re paying back the credit card,” she said.

    “I’ve got a lot of ambition to pay back as much of that credit card as we can because I think that’s the fair thing to do.”

    The Trans Mountain Corp. CEO also believes the project will be able to find a buyer. However, it will take time. 

    “This is a $30-plus billion dollar sale. This will be one of the biggest sales, if not the biggest sale, that’s ever occurred in the country,” Farrell added.

    “To the extent that we get everything ready to go for next spring, that gives us the time then through the spring and the fall to engage potential buyers and potential opportunities.

    “So, I would put having a conclusion on that until late in 2024, potentially early ‘25.”

    Chris Varcoe is a Calgary Herald columnist.

    cvarcoe@postmedia.com

    Article content

    Share this article in your social network

    Comments

    Postmedia is committed to maintaining a lively but civil forum for discussion and encourage all readers to share their views on our articles. Comments may take up to an hour for moderation before appearing on the site. We ask you to keep your comments relevant and respectful. We have enabled email notifications—you will now receive an email if you receive a reply to your comment, there is an update to a comment thread you follow or if a user you follow comments. Visit our Community Guidelines for more information and details on how to adjust your email settings.

    Advertisement 1

    This advertisement has not loaded yet, but your article continues below.

    [ad_2]

    Source link

    Tags: CEOexpansionexpectsMarchMountainopeningPipelinePotentialSaletransVarcoeyears
    Previous Post

    5 brilliant places to retire in New Zealand: 2023 UPDATE

    Next Post

    Best early October Prime Day laptop deals

    Next Post
    Best early October Prime Day laptop deals

    Best early October Prime Day laptop deals

    Leave a Reply Cancel reply

    Your email address will not be published. Required fields are marked *

    CATEGORIES

    • Africa
    • Asia Pacific
    • Australia
    • Business
    • Canada
    • Cryptocurrency
    • Economy
    • Entertainment
    • Europe
    • Gossips
    • Health
    • India
    • Lifestyle
    • Middle East
    • New Zealand
    • Politics
    • Sports
    • Technology
    • Travel
    • UK
    • USA

    LATEST UPDATES

    • How To Apply For A Visa For Armenia
    • Starmer pushed on EU youth mobility as Tory leadership rivals make final pitch – live
    • Aamir Khan offers condolences after ex-wife Reena Dutta’s father passes away

        © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.

        No Result
        View All Result

            © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.