    Varcoe: Alberta premier concerned about potential Trans Mountain delay

    kitsiosgeo by kitsiosgeo
    December 22, 2023
    in Canada
    0
    Varcoe: Alberta premier concerned about potential Trans Mountain delay

    [ad_1]

    Breadcrumb Trail Links

    PoliticsEnergyColumnistsBusiness

    ‘Everybody wants this project to be done. It’s going to make such a big difference,” says Alberta Premier Danielle Smith of the Trans Mountain expansion.

    Get the latest from Chris Varcoe, Calgary Herald straight to your inbox Sign Up

    Published Dec 22, 2023  •  Last updated 1 hour ago  •  5 minute read

    Trans Mountain
    Trans Mountain pipeline construction in Abbotsford, B.C., on November 29, 2023. Nick Procaylo/Postmedia

    Article content

    It doesn’t take a lot of imagination to envision what a two-year delay to the Trans Mountain pipeline expansion could mean to the province of Alberta or the Canadian oil sector.

    In the view of Alberta’s premier, it would be bad news.

    Article content

    “Very concerned about it, because I think there’s just so much pent-up demand” for additional pipeline capacity out of the province, Danielle Smith said in a year-end interview.

    Advertisement 2

    This advertisement has not loaded yet, but your article continues below.

    Calgary Herald

    THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

    Subscribe now to read the latest news in your city and across Canada.

    Unlimited online access to articles from across Canada with one account.Get exclusive access to the Calgary Herald ePaper, an electronic replica of the print edition that you can share, download and comment on.Enjoy insights and behind-the-scenes analysis from our award-winning journalists.Support local journalists and the next generation of journalists.Daily puzzles including the New York Times Crossword.

    SUBSCRIBE TO UNLOCK MORE ARTICLES

    Subscribe now to read the latest news in your city and across Canada.

    Unlimited online access to articles from across Canada with one account.Get exclusive access to the Calgary Herald ePaper, an electronic replica of the print edition that you can share, download and comment on.Enjoy insights and behind-the-scenes analysis from our award-winning journalists.Support local journalists and the next generation of journalists.Daily puzzles including the New York Times Crossword.

    REGISTER TO UNLOCK MORE ARTICLES

    Create an account or sign in to continue with your reading experience.

    Access articles from across Canada with one account.Share your thoughts and join the conversation in the comments.Enjoy additional articles per month.Get email updates from your favourite authors.

    Article content

    “Everybody wants this project to be done. It’s going to make such a big difference, not only to us being able to get more barrels sold, but also increasing the value of all of our barrels.”

    The spectre of a potential two-year delay in getting the $30.9-billion project finished — as Trans Mountain Corp. recently warned could be a worst-case scenario — would be negative news for producers who’ve been waiting a decade to see the project built.

    The Alberta government, which will benefit from increased oil production and more royalties tied to the incremental transportation capacity, would also feel the pinch.

    “Getting to the finish line as quickly as possible is where we need to be,” Smith said.

    “I’ll continue to cross my fingers that we get that line filled in the first quarter of next year.”

    Alberta Premier Danielle Smith
    Alberta Premier Danielle Smith attends a press conference at the Alberta Legislature in Edmonton on Tuesday Nov. 28, 2023. David Bloom/Postmedia file

    For many Albertans who thought the Trans Mountain construction story was quickly coming to an end — I lump myself in that group — that assumption may have been premature.

    Is there at least one more plot twist left in this long-running saga, or only a footnote to wrap up?

    The expansion of the existing 1,150-kilometre oil pipeline, which runs from the Edmonton area to the B.C. coast, has already turned into an epic slog.

    Calgary Herald Noon News Roundup

    Noon News Roundup

    Your weekday lunchtime roundup of curated links, news highlights, analysis and features.

    By signing up you consent to receive the above newsletter from Postmedia Network Inc.

    Thanks for signing up!

    A welcome email is on its way. If you don’t see it, please check your junk folder.

    The next issue of Noon News Roundup will soon be in your inbox.

    We encountered an issue signing you up. Please try again

    Article content

    Advertisement 3

    This advertisement has not loaded yet, but your article continues below.

    Article content

    The initial regulatory application to expand the existing pipeline was filed in 2013 and approved three years later.

    The expansion will almost triple the pipeline’s capacity to 890,000 barrels per day, moving more crude and refined products from Alberta to an export terminal in Burnaby, B.C.

    After the previous owners, Kinder Morgan Canada, appeared prepared to abandon the project, Ottawa purchased the line in 2018 for $4.4 billion.

    Construction was started, halted five days later due to a court decision, then restarted. The pandemic hit, followed by flooding, soaring inflation and supply chain issues.

    Since 2013, the project’s price tag has escalated 472 per cent.

    Today, the expansion of the pipeline is 98 per cent complete with only about three kilometres of pipe left to install.

    Related Stories

    Workers lay pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023. The company building the Trans Mountain pipeline has submitted evidence to support its claim that oil companies must pay more in tolls in light of the pipeline project's mounting costs.

    Trans Mountain project costs ’reasonably and justifiably incurred,’ company says

    Workers lay pipe during construction of the Trans Mountain pipeline expansion in Abbotsford, B.C. on Wednesday, May 3, 2023.

    Trans Mountain Corp. issued stop-work order for environmental non-compliance

    Contruction continues on the Trans Mountain Pipeline expansion project near Valemount, B.C., in 2020.

    Trans Mountain route change will ‘desecrate’ sacred site: Secwepemc knowledge keeper

    Trans Mountain Corp. CEO Dawn Farrell said in October she hoped to see the line being filled with oil in 2024, with the process starting at the end of January. Commercial operations were expected to begin by the end March.

    Advertisement 4

    This advertisement has not loaded yet, but your article continues below.

    Article content

    Yet, there are no easy slam dunks when it comes to building major pipelines. The project is facing challenges in British Columbia because of the hardness of the rock and water inflows.

    The Crown corporation applied in October to the Canada Energy Regulator (CER) for a variance related to a short 2.3-kilometre section, located along the Fraser River near Hope. It asked to install a smaller 30-inch pipe, instead of the planned 36-inch pipe, but the regulator turned it down.

    Trans Mountain made a new application last week, saying that if it continues with the original plan, there is a “significant risk the borehole will become compromised.”

    If the drilling fails and Trans Mountain has to implement an alternate plan, the completion schedule could be delayed.

    “Such a scenario would result in incremental environmental disturbance and delay the (project) schedule by approximately two years, causing billions of dollars in losses to Trans Mountain, in addition to substantial third-party losses,” the corporation stated in its latest filing.

    The interruption would lead to about $200 million a month in delayed revenues and $190 million in carrying charges, according to Trans Mountain.

    Advertisement 5

    This advertisement has not loaded yet, but your article continues below.

    Article content

    Tristan Goodman, head of the Explorers and Producers Association of Canada, said a lengthy delay would likely prompt oil companies to adjust their forecasted production estimates and fiscal budgets.

    “To have this happen at this point in time, to be honest, there’s no other way to describe this (than) preposterous,” Goodman said Thursday.

    “We are still hopeful that it isn’t a two-year delay, but it’s quite serious.”

    For producers and the province, there is a lot on the line.

    An economic impact assessment conducted by Ernst & Young for Trans Mountain last year concluded that once the expansion is operating, it’s expected to contribute $9.2 billion in additional GDP across Canada over a 20-year period.

    The project will generate about $40 billion of royalties and taxes to Alberta over two decades, Farrell said.

    Oil price forecast for Alberta

    The pipeline expansion will hand Canadian producers more export capacity, and it’s forecast to shrink the price spread between U.S. benchmark West Texas Intermediate (WTI) crude and Western Canadian Select heavy oil.

    The differential stood around US$20 a barrel earlier this week, according to ATB. The province’s fiscal update in November said completing Trans Mountain would help bring the discount down to around $14 to $15 a barrel in the next two years.

    Advertisement 6

    This advertisement has not loaded yet, but your article continues below.

    Article content

    S&P Global Commodity Insights expects Western Canadian oil supply to increase by 230,000 barrels per day (bpd) in 2024. Peak production in late 2024-25 could top 5.2 million bpd.

    “We still see the need for TMX in 2024 to be online for peak production,” said Kevin Birn, S&P’s chief analyst of Canadian oil markets.

    The industry and the province will be keenly watching what the CER decides on the new application.

    Trans Mountain has requested a decision by Jan. 9. On Thursday, the CER asked for additional information from the corporation.

    Earlier in the week, the CER released its written reasons for the first variance application, and said Trans Mountain didn’t adequately address pipeline integrity and environmental protection concerns.

    But it appears Trans Mountain has addressed most of the CER’s key issues in its new application, RBC Capital Markets analyst Greg Pardy said in a note.

    Similarly, a report by analyst Michael Dunn of Stifel said the revised application will likely quell the regulator’s concerns.

    “We must wait for the CER to formally respond with its approval,” the Stifel report states.

    “However, it looks like the expected startup of TMX . . . should clear what is (hopefully) the final regulatory hurdle.”

    Chris Varcoe is a Calgary Herald columnist.

    cvarcoe@postmedia.com

    Article content

    Share this article in your social network

    [ad_2]

    Source link

    Tags: AlbertaConcerneddelayMountainPotentialPremiertransVarcoe
    Previous Post

    RNC Heads Into Presidential Election Year With A Small Fraction Of What It Had Four Years Ago

    Next Post

    India-made LCA, LCH can boost clout in Global South: IAF Chief

    Next Post
    India-made LCA, LCH can boost clout in Global South: IAF Chief

    India-made LCA, LCH can boost clout in Global South: IAF Chief

    Leave a Reply Cancel reply

    Your email address will not be published. Required fields are marked *

    CATEGORIES

    • Africa
    • Asia Pacific
    • Australia
    • Business
    • Canada
    • Cryptocurrency
    • Economy
    • Entertainment
    • Europe
    • Gossips
    • Health
    • India
    • Lifestyle
    • Middle East
    • New Zealand
    • Politics
    • Sports
    • Technology
    • Travel
    • UK
    • USA

    LATEST UPDATES

    • How To Apply For A Visa For Armenia
    • Starmer pushed on EU youth mobility as Tory leadership rivals make final pitch – live
    • Aamir Khan offers condolences after ex-wife Reena Dutta’s father passes away

        © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.

        No Result
        View All Result

            © 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.